FRAME STAGE INSPECTION
FRAME STAGE INSPECTION
What we inspect at frame stage are according to the Australian Standards (AS 1684 Residential timber-framed construction, AS 1860-2006 Installation of particleboard flooring), the Building Code of Australia (BCA), VBA guide to standards and tolerances 2015 and the relevant engineer’s drawings and specifications.
We use a comprehensive inspection checklist including but not limited to the following:
-
The finish of the concrete slab is thoroughly checked for any exposed steel, damage or cracks
-
Floor levelness of each Storey to be checked according to VBA guide to standards and tolerances 2015
-
The size of the finished slab is measured to check it accords with the relevant floor plan
-
The room size and the height of all floors as per architecture plan
-
All doors and windows opening and position as per floor plan
-
Structural steel members like post, beam, lintel and bracing checked for support and fixings
-
All sections of the frame are checked to ensure it is level, plumb, straight and square
-
All sections of the roof trusses are correctly installed, tied down and adequately braced
-
Bottom plates that overhang the concrete slabs by more than 10mm need to be rectified
-
Wall frame member spacing are adequate with blocking & nogging installed for wall and ceiling linings
-
Location of under-slab services penetrations through the floor are in appropriate rooms
-
The installation of perimeter termite barrier where required